Hackerspace Setup Plan

Phase Overview

Phase Focus Rough Timeline Taskmaster
0 — Foundation Legal entity, bank account, lease signed Now!
1 — Shell Clean, prepare for decoration, basic power and internet Day -14
2 — Core build Zones defined, key tools installed, storage in place Day -7
3 — Soft launch First members in, iterate on layout and rules Day -5
4 — Public launch Launch party, open membership, full operations Day 0
5 — Ongoing Expand tools, refine processes, grow community Day 1+

specific checklists are broken down by phase number, and then checklisted in order!


SETUP WEEKEND

A group move-in event to configure the space!

Overview

As the move-in date approaches, all helpers are invited to a dedicated setup weekend — where we come together at the space and get everything configured as a group. Think of it as a move-in get-together: part hard work, part celebration.

What to expect

We set up and configure the space together, with everyone pitching in. 

Fuel for the work — expect food, good vibes, and a friendly atmosphere.

Come ready, in your grossest overalls or sweats — there's real setup work to get done!
Please make sure to talk to community manager @pan to get assigned a task master - based on your interests & skills!
YOU WILL BE PUT TO WORK, I'M SORRY BUT YOU GOTTA EARN THAT PIZZA

Timing

The setup weekend takes place closer to the move-in date. Keep an eye out for the specific date announcement — details will be shared with all helpers as the date approaches.


Zone Planning

Our space is divided into  into functional zones.  zoning prevents chaos and makes safety management possible, so please stick with them when planning! FOR HELPERS, During Setup, please get tasks from the respective task master for each zone!

N Zone Purpose Key Requirements Taskmasters Team
A Electronics bench Soldering, PCB work, prototyping Good lighting, ESD matting, fume extraction @superminaren
B Fabrication 3D printing, laser cutting, CNC Extraction, fire suppression nearby, noise isolation if possible @superminaren
C Workshop / heavy power tools dedicated power circuits, hard floor @superminaren
D Kitchen feed the hackers fridge, sink, dishwasher, moccamaster @pan
E Chill / social Sofas, kitchen, whiteboard Near entrance, separate from noisy zones @erlern
F Meeting / AV Area Talks, workshops, small events AV setup, moveable furniture, whiteboardable walls @claire
G Server / comms Networking, servers, radio Locked, climate considered, cable access @koponen
@superminaren

H Storage Member storage, shared materials, consumables Shelving, labelling system @pan

Phase 1 - Task Overview

# Task Owner Support Status Notes
1.1 Initial site visit and condition report TBD All founding members Document everything with photos
1.2 Deep clean — floors, walls, surfaces TBD Everyone Hire industrial cleaner if needed
1.3 Waste and debris removal TBD TBD
1.4 Power audit TBD TBD written report before any other electrical work
1.5 Circuit labelling TBD TBD Every breaker, every socket
1.6 Additional sockets / circuits TBD TBD Based on audit 
1.7 Lighting assessment and install TBD TBD Prioritise workshop and electronics areas
1.8 Internet — fibre install TBD TBD Lead time can be LONG
1.9 Basic networking (router, switch, Wi-Fi) TBD TBD Temporary setup is fine for Stage 1
1.10 Ventilation check TBD TBD Identify existing airflow; flag any blocked vents
1.11 Access control — primary entrance TBD TBD RFID or keypad minimum
1.12 Fire extinguishers installed TBD TBD At least CO2 + general; confirm placement
1.13 First aid kit TBD TBD Mounted, accessible, stocked
1.14 Safety signage TBD TBD Fire exit, first aid, no entry zones
1.15 Temporary storage (shelving / pallets) TBD TBD Enough to keep the floor clear
1.16 Phase 1 sign-off walkthrough TBD All board members Checklist walk, not a vibe check

Phase 2 - Task Overview

# Task Owner Support Status Notes
2.1 TBD TBD TBD
2.2 TBD TBD TBD
2.3 TBD TBD TBD
2.4 TBD TBD TBD  
2.5 TBD TBD TBD
2.6 TBD TBD TBD


A. Electronics Bench Set-Up

Taskmastered By @superminaren

# Task Owner Support Status Notes
A.1 Tool Wall superminaren TBD
A.2 Electronics Tables superminaren TBD
A.3 Overhead Lights superminaren TBD

B. Fabrication Set-Up

Taskmastered By @superminaren

# Task Owner Support Status Notes
B.1 TBD superminaren TBD

C. Heavy Set-Up

Taskmastered By @superminaren

# Task Owner Support Status Notes
C.1 TBD superminaren TBD

D. Kitchen Set-Up

Taskmastered By @pan

# Task Owner Support Status Notes
D.1 Vitvaror Installed & On - Fridge, Microwave, Dishwasher, Stove @pan TBD I NEED STRONG PEOPLE TO MOVE THEM
D.2 Appliances Installed & On- Kettle, Coffee Machine, @pan


D.3 MAKE COFFEE & TEA @pan

PEOPLE WORKING HARD NEED FUEL
D.4 Stock Cupboards
Need: mugs, cutlery, plates

D.5 Cleaning Equipment



E. Chill / Social Set-Up

Taskmastered By @erlern

# Task Owner Support Status Notes
E.1 TBD TBD TBD

F. AV Set-Up

Taskmastered By @claire

# Task Owner Support Status Notes
B.1 TBD superminaren TBD

G. Server Set-Up

Taskmastered By @koponen  @superminaren

# Task Owner Support Status Notes
B.1 TBD superminaren TBD

H. Storage Set-Up

Taskmastered By @pan

# Task Owner Support Status Notes
B.1 TBD @pan TBD