Hackerspace Setup Plan

Phase Overview

Phase Focus Rough Timeline Taskmaster
0 — Foundation Legal entity, bank account, lease signed Now!
1 — Shell Clean, safe,prepare for decoration, basic power and internet Day -14
2 — Core build Zones defined, key tools installed, storage in place Day -7
3 — Soft launch First members in, iterate on layout and rules Day -5
4 — Public launch Launch party, open membership, full operations Day 0
5 — Ongoing Expand tools, refine processes, grow community Continuous

specific checklists are broken down by phase number, and then checklisted in order!

Zone Planning

Our space is divided into  into functional zones.  zoning prevents chaos and makes safety management possible, so please stick with them when planning!

 

Zone Purpose Key Requirements Taskmaster
Electronics bench Soldering, PCB work, prototyping Good lighting, ESD matting, fume extraction
Fabrication 3D printing, laser cutting, CNC Extraction, fire suppression nearby, noise isolation if possible
Workshop / heavy power tools dedicated power circuits, hard floor
Kitchen feed the hackers fridge, sink, dishwasher, moccamaster
Chill / social Sofas, kitchen, whiteboard Near entrance, separate from noisy zones
Meeting / classroom Talks, workshops, small events AV setup, moveable furniture, whiteboardable walls
Server / comms Networking, servers, radio Locked, climate considered, cable access
Storage Member storage, shared materials, consumables Shelving, labelling system

Phase 1 - Task Overview

#TaskOwnerSupportStatusNotes
1.1Initial site visit and condition reportTBDAll founding membersDocument everything with photos
1.2Deep clean — floors, walls, surfacesTBDEveryoneHire industrial cleaner if needed
1.3Waste and debris removalTBDTBD
1.4Power auditTBDTBDwritten report before any other electrical work
1.5Circuit labellingTBDTBDEvery breaker, every socket
1.6Additional sockets / circuitsTBDTBDBased on audit 
1.7Lighting assessment and installTBDTBDPrioritise workshop and electronics areas
1.8Internet — fibre installTBDTBDLead time can be LONG
1.9Basic networking (router, switch, Wi-Fi)TBDTBDTemporary setup is fine for Stage 1
1.10Ventilation checkTBDTBDIdentify existing airflow; flag any blocked vents
1.11Access control — primary entranceTBDTBDRFID or keypad minimum
1.12Fire extinguishers installedTBDTBDAt least CO2 + general; confirm placement
1.13First aid kitTBDTBDMounted, accessible, stocked
1.14Safety signageTBDTBDFire exit, first aid, no entry zones
1.15Temporary storage (shelving / pallets)TBDTBDEnough to keep the floor clear
1.16Stage 1 sign-off walkthroughTBDAll board membersChecklist walk, not a vibe check